The 60,000-square-foot building is expected to be finished by the fall semester in 2024. The public will be invited to a Grand Opening celebration in the fall.
We are grateful to our community partners – including neighbors who live near the new building – for their time and energy in providing valuable feedback. The district offered many opportunities for the community to provide input throughout the project-planning phase, which began in June 2021. Neighbors who live near the Miller site were specifically invited to all of the community input sessions.
- June 2021 – Site evaluation study for Miller to confirm final site location
- June 22, 2021 – Presented site options study to the Board of Education
- July 20, 2021 – Two community listening sessions held on the site evaluation study
- Aug. 5, 2021 – Two community listening sessions held on the site evaluation study
- Aug. 10, 2021 – Site evaluation survey feedback was presented to the Board of Education with the data from the surveys and community sessions.
- Nov. 18, 2021 – Design Advisory Group (DAC) Meeting #1 – Programming Phase
- Dec. 9, 2021 – DAG Meeting #2 – Programming Phase
- Jan. 20, 2022 – DAG Meeting #3 – Schematic Design Phase
- Feb. 11, 2022 – Community Update Presentation on Programming
- April 14, 2022 – DAG Meeting #4 – Design Development Phase
- April 20, 2022 – Community Update Recording posted to 9R website
- May 18, 2022 – Neighborhood Design Open House – Flyers were passed out to all neighboring properties
- Aug. 17, 2022 – DAG Meeting #5 – 95% Construction Documents Phase
View the interior fly-through: https://www.youtube.com/watch?v=e8cbKWuH2fA
View the exterior fly-through: https://www.youtube.com/watch?v=7mt8B8WGUgM